Task history

Task history

Task history shows every task that left someone's task list: who had it, what it was for, when it was sent to the gun, when the work started and when it ended, who ended it and why. A task leaves the list when the work is done, and also when a supervisor takes it off, gives it to someone else, or closes or deletes its document. All of those are kept, so you can answer "who picked this order, and how long did it take?" or "why did this task disappear from Luis's gun?" without asking anyone.

Open it from Collaboration > Task history, under User tasks. It is for office Users; a user who belongs to a client cannot open it.

What is kept, and from when

From the day version 2.60.0 is installed, logisticaHQ keeps one row for every task that leaves a task list. Each row saves:

  • The task number (TSK-…), its type and what it was for: the order, bin or pallet.
  • Who it was assigned to, and when it was sent to the gun.
  • When it ended, who ended it, and how it ended (see below), with a short note when there is one, such as "document deleted".

History starts the day 2.60.0 is installed. Tasks that ended before that day were not recorded and are not recovered. The row keeps the numbers and names as they were on the day, so it still reads correctly after a document is deleted or a person leaves. The history is kept with no end date.

Recording never stops the work. A task is recorded in the same moment it leaves the list. If logisticaHQ cannot read who had the task or where it stood, the row is kept without that detail. If a task cannot be recorded at all, the pick, move or count still finishes, and Setup > System > Logs has a line starting "Task history:" that names the task.

Turning the recording off. An administrator can stop the recording in Setup > System > Configuration, Business, Collaboration, Stop Recording Task History. It starts off, so tasks are recorded. While it is on, tasks that end are not recorded and never appear later; turn it off again to go back to recording. Use it only if the recording gets in the way of the work.

Looking something up

The screen opens on everyone's completed tasks for today, the most recently ended first. Use the filters to change what it shows:

  1. Person: type a name and pick the person, or leave it empty (Everyone). The person is the one the task was assigned to, not the one who ended it.
  2. Period: Today, Last 7 days, This month, Last month or Custom… (then pick a From and a To day; both days are included). The period is when the task ended, in your own time.
  3. Task type: All types or one type: Receiving (PO), Picking, Return, Truck Load, Master Truck Load, Production, Product move, Bin move, Pallet move, Cycle Count, QC inspection or Marketplace pick.
  4. Outcome: Completed (the default), All outcomes, or one of the other ways a task ends.

Looking up one person shows people figures. While people figures are kept for administrators (the default), only administrators can look up a person; anyone else sees a sentence saying so in place of the list. The list of everyone's tasks is open to every office user.

How a task ended

OutcomeIt means
CompletedThe work was done: the move or count was posted on the gun, the order was picked, the receipt or return was received, the production order was picked or produced, the Truck Load shipped, the QC inspection was released, or the person finished their zone of a Marketplace pick.
CancelledA supervisor took the task off before the work was done: deleted it in User tasks, used Unassign operator on the document, or unwaved, unallocated or suspended a pick ticket or production order before anything was picked or produced.
ReassignedThe task was given to someone else: the document was assigned to another person, or a count assignment was reassigned (its note names the new person).
Document closedThe document was closed or cancelled without the work done: an order closed before it was picked or received, a production order closed with nothing picked or produced, a QC inspection replaced by a new one or cancelled, a Truck Load joined to a master load, or a pick ticket moved onto an LTL load.
ClearedHousekeeping: the document or the user was deleted, a count's location no longer exists, or a Marketplace task was left over after the work finished or the load shipped. A Marketplace clean-up is done by logisticaHQ itself, so Ended by is empty.
UnknownThe task ended in a way logisticaHQ does not name yet. It should not happen; it is written to the log so it can be fixed. Unknown is shown in the list but is not offered as a filter.

Point at the outcome to read its note, when it has one.

Reading the screen

Above the list, four tiles describe the whole period, person and type you chose. They ignore the Outcome filter, so Not completed still counts while the list shows only completed tasks.

TileWhat it shows
CompletedHow many tasks were completed, and by how many people.
Average time to finishFrom Started to Ended, over the latest 500 completed tasks of your search that have a start. Cycle counts, pallet moves, bin moves, Truck loads and Marketplace picks have no start, so they are not part of it. Point at either average tile to see this note.
Average wait before startFrom Sent to Started, over the same tasks.
Not completedHow many tasks ended any other way: cancelled, reassigned, document closed, cleared or unknown.

The list has one row per task, the most recently ended first, 50 rows to a page (use Previous and Next).

ColumnWhat it shows
TaskThe task number (TSK-…).
TypeWhat kind of task it was.
ForThe order, bin or pallet. A Cycle Count task also shows the count assignment it came from (CNT-…).
Assigned toThe person who had the task.
SentWhen the task was sent to the gun, in your time.
StartedWhen the work started (see below), or a dash when it is not known.
EndedWhen the task left the list.
Time to finishFrom Started to Ended: "45 s", "12 min", "1 h 05 min" or "2 d 3 h", always rounded down. A dash when there is no start.
Ended byWhose action ended it, by name, the same way Assigned to shows it: the person who finished the work on the gun, or the supervisor who cancelled, reassigned or closed it. A person who has since been deleted shows their username. A dash when logisticaHQ ended it itself.
How it endedThe outcome (see above).

How Started is worked out

The gun does not record the moment a person opens a task, so Started is the assigned person's first scan for that task between the moment it was sent and the moment it ended. Someone else's scan of the same bin does not count. Cycle counts, pallet moves and bin moves are saved only at the moment the task ends, so they have no start: that moment says when the work ended, not when it began. For the same reason, any task finished in a single step, such as a Product move done in one go or an order with one pick, shows no start.

Task typeStarted is
Receiving (PO), ReturnThe first item received on one of the document's lines.
PickingThe first item picked into a tote for one of the order's lines.
Production, QC inspectionThe first scan recorded on that production order or inspection.
Product moveThe first move out of that bin or pallet, when the move was done in parts. A move done in one go has no start.
Cycle Count, Pallet move, Bin moveNo start: the gun saves the count, or moves the whole pallet or bin, at the moment the task ends, and records nothing before that. These rows show a dash and are left out of both averages.
Truck Load, Master Truck Load, Marketplace pickNo start: no scan ties to the task before it ends. These rows show a dash and are left out of both averages.

A task that was cancelled or cleared before anybody scanned anything has no start either.

The Task history tab on User details

Open a user in Setup > System > Users and choose the Task history tab to see that person's tasks: the same tiles and list, with its own Period, Task type and Outcome filters, Export and Print. It follows the same people-figures rule as looking up a person.

Print

Print opens the task history as a PDF in a new tab, ready to print or save. It holds the whole result of your search, not only the page on screen: the person (or Everyone), the period, type and outcome, the tiles and every task. It prints in your language, and a task logisticaHQ ended itself shows System under Ended by. A search that finds more than 5,000 tasks is not printed; choose a shorter period or one person, and print again. If your browser blocks the new tab, the PDF is downloaded instead.

To change how it looks (the logo, the columns, the wording), open Setup > System > Tenant, Document Printing, and edit Task history in the report designer. Every history printed after that uses your design; Reset goes back to the standard one.

Export

Export saves the rows on screen to Excel, with the type, what it was for and how it ended as the screen shows them. Time to finish is exported in seconds so it sorts correctly. To export a long history, narrow the period first, or go through it page by page.

Troubleshooting

What you seeWhy, and what to do
"No tasks found for this period. Task history starts the day version 2.60.0 is installed."No task ended in that period with that outcome, or they ended before version 2.60.0 was installed. Choose All outcomes and a longer period to be sure.
A task I finished a minute ago is not listedReload the page. Check that the period includes today and that Outcome is Completed or All outcomes.
A task I know ended is not listed at all, with any period and outcomeCheck Stop Recording Task History in Configuration (Business, Collaboration): tasks that end while it is on are not recorded. Otherwise look in Setup > System > Logs for a line starting "Task history:" that names the task; send it to your administrator.
A row has no name under Assigned to or Ended bylogisticaHQ could not read that detail when the task ended, and kept the row without it. Setup > System > Logs has a line starting "Task history:" that says why.
Started shows a dashCycle counts, pallet moves, bin moves, Truck loads, Master truck loads and Marketplace picks have no start, and neither does a task finished in a single step, such as a Product move done in one go or an order with one pick. For other tasks, nobody assigned to it scanned anything for it before it ended.
The tiles count tasks the list does not showThe tiles cover every outcome in the period; the list follows the Outcome filter.
A task shows Cancelled but the order is still openA supervisor took the task off the person (User tasks, Unassign operator, unwave or unallocate). Assign the order again to send a new task.
Looking up a person says the figures are kept for administratorsYour company keeps people figures for administrators. Ask an administrator, or look at everyone's tasks instead.
Print says the search found too many tasksOne printout holds up to 5,000 tasks. Choose a shorter period or one person, then print again.
Nothing happens when I press PrintYour browser may have blocked the new tab. Allow pop-ups for logisticaHQ, or look in your downloads: the PDF is saved there.
A row says UnknownThe task ended in a way logisticaHQ does not name yet. Tell your administrator; the case is in the log.
The screen says you cannot see the task historyTask history is for office Users; a user who belongs to a client cannot open it.

See also Count assignments and Count history.